https://www.ogj.com/articles/print/volume-116/issue-2/special-report-worldwide-pipeline-construction/near-term-pipeline-plans-nearly-double-future-slows.html
Planned pipeline construction to be
completed in 2018 nearly doubled from the previous year, with expected
crude and natural gas project completions more than making up for
smaller projected products pipeline numbers. Future planned mileage
slipped slightly overall as completion of some of the gas and crude
projects moved into the current year.
Operators plan to complete installation of
14,657 miles in 2018 alone (Table 1), with natural gas plans (11,936
miles) making up more than 81% of the total, based on data collected by
Oil & Gas Journal. By contrast, crude and products pipelines made up
nearly 60.5% of total planned construction as recently as 2013.
As 2017 began, operators had announced plans
to build more than 33,600 miles of crude oil, product, and natural gas
pipelines extending into the next decade, a roughly 2.6% decrease from
data reported the prior year (OGJ, Feb. 6, 2017, p. 62). The softer
plans for beyond 2018 moderated the slide that occurred over the past 2
years, as the energy market seems to have found its bottom for the time
being. Sharp reductions in long-term gas pipeline plans in the Middle
East erased gains in other regions.
As a whole, combining both current-year and
forward estimates (Fig. 1), increases in planned construction in the US,
Europe, Asia-Pacific, and Africa outweighed decreases elsewhere.
Outlook
EIA forecast world liquid fuels
consumption to increase by 18.9% through 2040 (using a 2015 baseline), a
period that encompasses the long-term pipeline construction projections
described here. This rate of growth was down sharply from EIA's
year-earlier forecast, which called for a 34.4% increase from a 2012
baseline.
Demand growth will be strongest, according to
its September 2017 International Energy Outlook (IEO), among non-OECD
countries, growing at a base-case 1.3%/year rate compared with a 3%
decrease in the OECD over the same period. This growth will be led by
Asia, with its non-OECD countries making up 80% of the total worldwide
demand growth, as both China and India experience rapid industrial
expansion and increased transportation demand.
Transportation consumption of liquid fuels in
China will grow 36% by 2040, according to EIA. India's
transportation-driven demand will more than double, with 142% growth
expected.
EIA raised its total Asian liquid fuels
demand slightly to 46.6 million b/d from the 46.4-millon b/d previously
forecast, all growth coming from the non-OECD countries. Through 2050,
OECD Asia demand growth is expected to remain flat as the already larger
non-OECD demand in the region expands by 1.7%/year. EIA expects liquid
fuels demand in Japan to fall 0.9%/year between 2015 and 2050.
Non-OECD Asia GDP growth slipped to 3.9%/year
(from 4.2%) through 2050. India's growth, though still the world's
fasteset, slows to 5.0%/year through 2040 from 5.5% in the previous IEO,
and to 4.3% through 2050. China's GDP is expected to grow by 4.3%/year
through 2040, considerably slower than the 9.6% growth rate over the
past 10 years. EIA expects a 3.0% global growth rate through 2040, down
from 3.3% last year. The agency expects 2.8%/year global GDP growth
through 2050.
The EIA Annual Energy Outlook (AEO) 2017
forecast relatively flat US petroleum consumption through 2040,
remaining below its 2005 peak as improved energy efficiency offsets
growth in transportation and industrial activity. Consumption of
petroleum and other liquids reaches a peak of 20.19 million b/d in 2019
(from a 2015 base of 19.55), dropping to 18.96 million b/d in 2033
before rising to 19.34 in 2040 and a new peak of 20.57 million b/d in
2050.
EIA projects US crude production leveling off
between 10 and 11 million b/d through 2040, despite higher prices, as
recent productivity gains plateau. Production first reaches 10 million
b/d in 2021 and peaks at 10.55 million b/d in 2029.
The agency projects US dry natural gas
production to continue growing at nearly 4%/year through 2020, reaching
30.79 tcf that year, with growth tapering off to an average rate of
1%/year through 2040 as export growth moderates and efficiency gains
occur. EIA predicts 2040 production of 37.74 tcf.
OGJ tracks applications for gas pipeline
construction to the US Federal Energy Regulatory Commission (FERC).
Applications filed in the 12 months ending June 30, 2017 (the most
recent 1-year period surveyed), totaled fewer miles despite the general
upturn in plans.
• 529 miles of gas pipeline were proposed for
land construction. For the earlier 12-month period ending June 30,
2016, more than 2,470 miles were proposed for land construction.
• FERC applications for new or additional
compression horsepower at the end of June 2017 also fell sharply,
totaling almost 600,000 hp from more than 2.2 million hp in June 2016.
Bases, costs
For 2018 only (Table 1), operators
plan to complete roughly 14,560 miles of oil and gas pipelines worldwide
at a cost of nearly $95 billion. For 2017 only, companies had planned
roughly 7,750 miles at a cost of more than $59 billion.
For projects completed after 2018 (Table 2),
companies plan to lay more than 33,650 miles of line and spend roughly
$215 billion. When these companies looked beyond 2017 last year, they
anticipated spending roughly $264 billion to lay more than 34,500 miles
of line. Land construction costs fell in the meantime from $7.65
million/mile to $5.94 million/mile.
• Projections for 2018 pipeline mileage
reflect only projects likely to be completed by yearend 2018, including
construction in progress at the start of the year or set to begin during
it.
• Projections for mileage after 2018 include
construction that might begin in 2018 but be completed later. Also
included are some long-term projects judged as probable, even if they
will not break ground until after 2018.
Based on historical analysis and a few exceptions and variations
notwithstanding, these projections assume that 90% of all construction
will be onshore and 10% offshore and that pipelines 32 in. OD or larger
are onshore projects.
Following is a breakdown of projected costs, using these assumptions and OGJ pipeline-cost data:
• Total onshore construction (14,189 miles) for 2018 only will cost roughly $84 billion:
-$690 million for 4-10 in.
-$8.0 billion for 12-20 in.
-$16.7 billion for 22-30 in.
-$58.8 billion for 32 in. and larger.
• Total offshore construction (477 miles) for 2018 only will cost more than $10.5 billion:
-$286 million for 4-10 in.
-$3.3 billion for 12-20 in.
-$6.9 billion for 22-30 in.
• Total onshore construction (32,710 miles) for beyond 2017 will cost more than $194 billion:
-$15.6 billion for 12-20 in.
-$34.9 billion for 22-30 in.
-$144 billion for 32 in. and larger.
• Total offshore construction (943 miles) for beyond 2018 will cost nearly $21 billion:
-$6.4 billion for 12-20 in.
-$14.5 billion for 22-30 in.
Action
What follows is a quick rundown of some of the major projects in each of the world's regions.
Pipeline construction projects mirror end
users' energy demands, and much of that demand continues to center on
natural gas, with the industry remaining focused on how to get that gas
to market as quickly and efficiently as possible. The following sections
look at both natural gas and liquids pipelines.
US, Canada activity
Gas, NGL
TransCanada Alaska, the state's
licensee to build a natural gas pipeline from Alaska's North Slope,
received state clearance May 2, 2012, to change the project's focus to a
large-diameter pipeline to an Alaska tidewater site for in-state use,
liquefaction, and export. The pipeline would transport an estimated
3-3.5 bcfd of gas about 800 miles to Valdez, Alas., where shippers could
liquefy the gas in a plant constructed by others and send it on tankers
to US and international markets.
The move came after TransCanada Corp. and the
North Slope's three major producers-BP PLC, ConocoPhillips, and
ExxonMobil Corp.-announced Mar. 30, 2012, that they would work together
to commercialize ANS gas by focusing on large-scale exports from
south-central Alaska as an alternative to a pipeline through Alberta to
markets in the US Lower 48. The four companies completed the project's
concept selection phase in February 2013.
The US Department of Energy (DOE) in November
2014 granted the project, now called Alaska LNG and including the
Alaska Gasline Development Corp. (AGDC), authority for exports to
countries covered by free-trade agreements (FTA), approving exports to
non-FTA destinations like Japan, China, India, and Taiwan in May 2015.
Alaska bought TransCanada's share of the
project in November 2015 and the producing companies told the state in
2016 that weak market conditions did not warrant proceeding with the US
Federal Energy Regulatory Commission (FERC) application and costly
design work in 2017. Alaska Gov. Bill Walker said the state would take
over the project to keep it on schedule while seeking to reduce costs
and searching for both investors and customers.
Chinese and Alaskan officials signed a
five-party, $43-billion joint development agreement for the Alaska LNG
project in November 2017. China Petrochemical Corp. (Sinopec), CIC
Capital Corp., and Bank of China agreed to work with AGDC and the state
government on LNG marketing, financing, investment modeling, and
establishing China content in Alaska LNG.
Large gas pipeline projects in Canada,
centered on shipping material from shale plays in Alberta and British
Columbia to the Pacific coast for liquefaction and export, faltered as a
number of LNG projects were cancelled.
In early 2013, Chevron Canada Ltd. bought 50%
of Kitimat LNG and the proposed Pacific Trail Pipeline. Pacific Trail
is a 290-mile, 36-in. OD pipeline which would move gas to the Kitimat
LNG terminal. The British Columbia government in July 2013 extended
Chevron and partner Apache's window to start construction on the line to
2018. Woodside bought Apache's interest in Kitimat LNG in late 2014
(OGJ Online, Dec. 15, 2014). A final investment decision on the plant
was still pending as of December 2017, the pipeline's fate likely
hanging in the balance.
Spectra Energy Corp., meanwhile, lost the
basis for its 42-in. OD, 525-mile Westcoast Connector gas pipeline from
northeast British Columbia to Royal Dutch Shell PLC's planned LNG plant
in Prince Rupert, BC, when the major cancelled the project. Shell's
cancellation was followed by Petronas halting development of Pacific
Northwest LNG and Nexen stopping plans for its Aurora LNG plant, both of
which were also planned for the Prince Rupert area.
TransCanada's proposed Prince Rupert Gas
Transmission (PRGT) project to provide gas to Pacific Northwest LNG,
however, was proceeding as of January 2018 despite the liquefaction
project's cancellation, the pipeline company evaluating other options
for the system. The 470-mile, 48-in. OD PRGT is designed to deliver 2.1
bcfd from TransCanada's Nova Gas Transmission Ltd. Operations could
begin as early as 2019.
Projects to move natural gas liquids to
market, meanwhile, faced headwinds in the US. Kinder Morgan Energy
Partners LP (KMEP) and MarkWest Utica EMG LLC's proposed Utica Marcellus
Texas Pipeline (UMTP) Y-grade transportation project from the Utica and
Marcellus shales to Mont Belvieu, would have an initial design capacity
of 150,000 b/d and be expandable to 430,000 b/d. The first 964 miles of
the line would consist of converted Tennessee Gas Pipeline system, with
200 miles of new-build between Natchitoches, La., and Mont Belvieu, and
120 miles of laterals to provide basin connectivity. The companies are
targeting a fourth-quarter 2018 in-service date but municipal opposition
along its route might cause this to be delayed.
FERC ruled in September 2017 that KMEP could
proceed with abandonment of its gas line, a necessary regulatory step in
the conversion process. New legal challenges, however, were filed in
response, with FERC allowing the project to proceed in the meantime.
Project Mariner, announced in 2010 by Sunoco
Logistics Partners LP and MarkWest Energy Partners LP to move Marcellus
shale NGLs to market, began operations on Mariner West (shipping 65,000
b/d of ethane to Sarnia, Ont.) in 2013. The 70,000 b/d Mariner East
segment began propane operations in fourth-quarter 2014 and ethane
operations in first-quarter 2016, moving the liquids to the US Atlantic
Coast for shipment to Gulf Coast chemical producers and European
markets. The combined projects included just 85 miles of new pipeline,
using existing Sunoco infrastructure for the balance of each route.
The company in late 2014 announced it had
received sufficient shipper interest to move ahead with its 275,000 b/d,
306-mile Mariner East 2 pipeline, largely paralleling the route of the
first line. Mariner East 2 will use parallel 20-in. and 16-in. OD
pipelines in the same right of way, the latter dubbed Mariner East 2X.
Mariner East 2 will carry propane, ethane, and butane; 2X all three of
these as well as C3+, natural gasoline, and condensate, or any
combination of these products.
Sunoco expects to put the 20-in. line in
service second-quarter 2018 and complete work on the 16-in. line by
yearend 2018. but this might be delayed by community and legal
challenges. Pennsylvania's Department of Environmental Protection (DEP)
in January 2018 ordered Sunoco to stop construction until it meets
requirements of a DEP order addressing impacts to private wells,
construction authorization, and controls to minimize inadvertent
releases.
Natural gas pipeline projects in the
northeast US also continued to face delays caused by community
opposition. EQT Midstream Partners' Mountain Valley Pipeline (303 miles,
42-in. OD, northwestern West Virginia to southern Virginia) is
scheduled for a fourth-quarter 2018 startup but as of January 2018 still
faced landowner suits regarding property access. National Fuel Gas
Supply Corp.'s Northern Access Project (96.49 miles, 24-in. OD, McKean
County, Pa., to Erie County, NY), announced more than 2 years ago,
remains in limbo following an April 2017 denial by New York's Department
of Environmental Conservation of its water quality permits. National
Fuel has asked FERC to determine whether it can proceed without the
permits.
Enbridge in June 2017 withdrew its FERC
application to complete Access Northeast (97 miles, expansion of
existing system in New York, Connecticut, and Massachusetts) following
opposition. Dominion's Atlantic Coast (600 miles, 42-in. OD, West
Virginia to North Carolina) pipeline's erosion and sediment control plan
was denied by North Carolina's Division of Energy, Mineral, and Land
Resources in January 2018.
The Permian basin has been the area of most
rapid growth in US hydrocarbon production over the past year, reflected
by an accompanying scramble to build new pipelines between Permian
developments and both consuming centers and export destinations.
Kinder Morgan Texas Pipeline LLC (KMTP), DCP
Midstream LP, and an affiliate of Targa Resources Corp. will build the
Gulf Coast Express Pipeline Project (GCX). About 85% of the project's
1.92-bcfd capacity is subscribed and committed under long-term, binding
transportation agreements. GCX's mainline portion consists of roughly 82
miles of 36-in. OD pipeline and 365 miles of 42-in. pipeline starting
at the Waha Hub near Coyanosa, Tex., in the Permian basin and ending
near Agua Dulce, Tex. GCX's Midland Lateral includes about 50 miles of
36-in. pipeline and associated compression, connecting with the GCX
mainline. KMTP expects GCX to be in service in October 2019, pending the
receipt of necessary regulatory approvals. Construction is expected to
begin this quarter.
Sempra LNG & Midstream and Boardwalk
Pipeline Partners LP are planning the Permian-Katy Pipeline project
(P2K). The roughly 470-mile, 42-in. OD natural gas pipeline is proposed
to transport up to 2 bcfd from the Waha Hub in the Permian basin to
Katy, Tex., and on to the Houston Ship Channel. A phased-in startup
could begin as early as December 2019.
Epic Y Grade Pipeline LP, a subsidiary of
Epic Y Grade Services LP and Epic Midstream Holdings LP, has agreed with
BP Energy Co., a subsidiary of BP PLC, for the latter to anchor a
650-mile NGL pipeline liking the Permian and Eagle Ford regions to Gulf
Coast refiners, petrochemical companies, and export markets (Fig. 2).
Construction already has begun on the Epic
NGL Pipeline, which will have throughput capacity of at least 220,000
b/d with multiple origin points in the Delaware and Midland basins.
Destinations will include interconnects near Orla, Benedum, and Corpus
Christi, Tex., where Epic's affiliate plans to build a complex with
multiple 100,000-b/d fractionators. Epic plans to reach full capacity in
2019.
Enterprise Products Partners likewise plans
to have its 250,000 b/d Shin Oak NGL pipeline in service by 2019,
running 571 miles of 24-in. OD pipe from the Permian to the US Gulf
Coast.
Tellurian Inc. plans to develop a natural gas
pipeline network consisting of the previously announced Driftwood
Pipeline (DWPL) and two other lines. DWPL, a 96-mile, 48-in. OD
pipeline, is expected to be in-service mid-2021, delivering 4 bcfd from
Gillis, La., to Driftwood LNG. DWPL is in permitting with FERC.
Tellurian's Permian Global Access Pipeline
would be a 625-mile, 42-in. OD pipeline transporting 2 bcfd from the
Waha Hub in Pecos County, Tex., and Permian and associated shale plays
around Midland, Tex. to interconnects near Gillis, La. Proposed delivery
systems include the Creole Trail Pipeline, Cameron Interstate Pipeline,
Trunkline Gas Co., Texas Eastern, Transco, Tennessee Gas Pipeline,
Florida Gas Transmission, and DWPL, among others.
The company's Haynesville Global Access
Pipeline would cross 200 miles with 42-in. OD pipeline, transporting an
additional 2 bcfd to the same interstate pipelines near Gillis. Both of
these lines are expected to enter in service during 2022.
NAmerico Partners LP's proposed Pecos Trail
pipeline would ship more than 1.85 bcfd through 468 miles of 42-in. OD
pipe from the Permian basin to Corpus Christi by 2020.
Crude
Enbridge Inc.'s $7.5-billion Line 3
Replacement (L3R) Program, which the company describes as its largest
project ever, faces continued delays. L3R will replace the majority of
Enbridge's existing 34-in. OD Line 3 crude pipeline with new 36-in. OD
pipeline on both sides of the Canada-US border, a total of 1,031 miles,
doubling its capacity to 760,000 b/d. Enbridge will decommission the
existing Line 3 once the new line is complete.
On the Canadian side of the border Enbridge
will replace most of the existing Line 3 between its Hardisty Terminal
in east-central Alberta and Gretna, Man. In the US, Enbridge will
replace Line 3 between Neche, ND, and Superior, Wisc.
Canada's federal government approved L3R
construction in late 2016 (OGJ Online, Nov. 30, 2016). Enbridge
originally expected the new line to enter service second-half 2017, but
the company in December 2017 described its start date as uncertain and
perhaps as late as November 2019, given mounting resistance inside the
US.
Canada also approved TransCanada's Trans
Mountain Expansion project (TMEP) to move crude west from Alberta. The
project would use 36-in. OD pipe to twin 980 km of its existing Trans
Mountain pipeline. Even while granting the approval, however, Prime
Minister Justin Trudeau said "we are under no illusion that the decision
will [not] be bitterly disputed," recognizing the likelihood of
continued protests and litigation (OGJ Online, Nov. 30, 2016).
TMEP will add 300,000 b/d of the Trans
Mountain pipeline system, bringing total capacity to 890,000 b/d. The
Westridge marine terminal at Trans Mountain's end in Burnaby, BC, will
be expanded with three new berths. Storage additions will include 14 new
tanks at an existing terminal in Burnaby and five new tanks at an
existing terminal in Edmonton.
TransCanada planned to begin construction in
September 2017 and place the expansion into service in late 2019. In
January 2018, however, the company said the project could be as much as a
year behind schedule due to permitting delays, moving its projected
in-service date to as late as December 2020.
The company in October 2017 cancelled its
Energy East pipeline project. Energy East plans called for 4,500 km of
pipeline capable of shipping 1.1-million b/d of crude from Hardisty,
Alta., and Moosomin, Sask., to refineries in eastern Canada and marine
terminals in Cacouna, Que., and Saint John, NB. About 3,000 km of the
pipeline would have consisted of TransCanada PipeLines Ltd.'s converted
Canadian Mainline natural gas pipeline, with the other 1,500 km
new-build miles.
TransCanada concluded on open season for its
long-sought (originally planned to enter operations in 2012) 830,000-b/d
Keystone XL pipeline in January 2018, securing about 500,000 b/d of
firm, 20-year commitments and describing the results as sufficient for
the project to proceed. It plans to begin primary construction in 2019,
pending a final investment decision.
US President Donald Trump issued a
presidential permit for the project in March 2017. The Nebraska Public
Service Commission in November 2017 approved Keystone XL's route. But
land owners have filed suit against the state, protesting the new route,
and outstanding permits remain.
The delays and cancellations of pipelines
designed to move Canadian oil to market affected both Canadian crude
prices and inventories at Cushing, Okla., according to the EIA. The Jan.
18, 2018, edition of its 'This Week in Petroleum,' the agency reported
prices of Western Canada Select as trading at their deepest discounts to
West Texas Intermediate in nearly 3.5 years and noted that crude stocks
in Cushing had declined by 22 million bbl (34%) since the beginning of
November 2017 and were 17% below their 5-year average as Jan. 12, 2018.
Permian basin growth inspired a flurry of
crude pipeline development in addition to the NGL projects. Buckeye
Partners LP subsidiary South Texas Gateway Pipeline LLC launched a
binding open season for a 600,000 b/d pipeline from the Permian basin
and Gardendale, Tex., to Corpus Christi, Ingleside, and Houston, Tex.
Phillips 66 and Enbridge Inc. are holding an
open season for the Gray Oak Pipeline, a 385,000-b/d system that will
carry Permian basin production for export and to Texas refineries in
Corpus Christi, Freeport, and Houston. Shippers will have the option to
select from origination stations in Reeves, Loving, Winkler, and Crane
counties in West Texas. The companies expect Gray Oak Pipeline to have
an initial capacity of 385,000 b/d and will evaluate expansion of the
system based on shipper interest during the open season. The pipeline
system is expected to enter service second-half 2019.
Epic is planning a Permian-to-Corpus Christi
crude oil pipeline, largely paralleling the path of its Y-grade project
(Fig. 2). The 700-mile line would carry as much as 550,000 b/d.
Magellan Midstream in December 2017 proposed a
645-mile, 24-in. OD pipeline from Crane, Tex., to Three Rivers to
Corpus Christi, moving both Permian and Eagle Ford crude to the coast.
The 350,000 b/d line would include a 200-mile branch from Three Rivers
to Houston and is planned to enter service in 2019.
Plains All American's Cactus II pipeline
would run 515 miles of 24-in. OD pipe from Wink, Tex., to McCamey and
then from McCamey to Ingleside-Corpus Christi, expanding the current
Cactus system's capacity to 575,000 b/d from 390,000 b/d.
Latin America
Substantial growth of US gas exports
to Mexico has prompted rapid construction of new transmission capacity
both between the countries and inside Mexico. Infraestructura Marina del
Golfo (IMG)-TransCanada Corp.'s joint venture with Sempra Energy
subsidiary IEnova-will build, own, and operate the 42-in. OD, 497-mile
Sur de Texas-Tuxpan natural gas pipeline in Mexico. A 25-year gas
transportation service contract for 2.6 bcfd with Comision Federal de
Electricidad (CFE), Mexico's state-owned power company, supports the
project, expected to enter service in late 2018. The pipeline will begin
offshore in the Gulf of Mexico at the border point near Brownsville,
Tex., and extend along the coast to Tuxpan, Veracruz, Mexico. It will
connect with Cenegas's pipeline system in Altamira and with
TransCanada's Tamazunchale and Tuxpan-Tula pipelines, among other
transport systems in the region.
Sur de Texas will be supplied by gas from the
2.6-bcfd Valley Crossing Pipeline, to be built by Spectra Energy under a
CFE contract. Valley Crossing will extend 168 miles from Agua Dulce hub
in Nueces County, Tex., to Brownsville.
TransCanada will own 60% of the $2.1-billion
Sur de Texas-Tuxpan project and operate it. IEnova will own the other
40%. Spectra is sole owner of the $1.5-billion Valley Crossing line.
TransCanada previously won bids to build and
operate the Tuxpan-Tula (OGJ Online, Nov. 11, 2015) and the Tula-Villa
de Reyes (OGJ Online, Apr. 11, 2016) lines. The 36-in. OD, 155-mile
Tuxpan-Tula pipeline, carrying 886 MMcfd, is already operating.
Tula-Villa de Reyes will start in 2018, moving 550 MMcfd across 174
miles through 36-in. OD pipe. The 220-mile, 42-in. Villa de
Reyes-Aguascalientes-Guadalajara line is also scheduled to enter service
in 2018.
Refined products shipments from the US to
Mexico have also grown. Howard Midstream's Dos Aguilas pipeline will
carry clean products 287 miles from Corpus Christi, Tex., to Monterrey,
Mexico. Its four 12-in. OD sections comprise the Border Express pipeline
from Corpus to Laredo, Tex., the Borrego from Laredo to the
international border crossing (a total of 151 miles), Poliducto Frontera
from the border to Nuevo Laredo, Mexico, and Poliducto del Norte from
Nuevo Laredo to Monterrey (136 miles). Service is expected in 2018.
Pampa Energia subsidiary TGS plans to build a
more than 700 mile transmission pipeline system in Argentina to move
natural gas produced in the Vaca Meurta shale by companies including YPF
SA, Tecpetrol, Dow Argentina, ExxonMobil Corp., Chevron, and Statoil.
The 4-million cu m/year pipeline is expected to enter service in 2019.
Asia-Pacific
OAO Gazprom and China National
Petroleum Corp. (CNPC) in 2014 signed a 30-year natural gas supply
contract reportedly worth $400 billion. The contract stipulates that 38
billion cu m/year (bcmy) will be supplied from Russia to China. It
includes provisions for a price formula linked to oil prices and a
take-or-pay clause. Gas will be delivered via the 2,465-mile Power of
Siberia trunk line (Fig. 3). Work on the 56-in. OD line began in
September 2014, with construction of the Chinese section beginning June
2015.
The companies in December 2015 agreed on
design and construction of the pipeline's cross-border section under the
Amur River. They expect to commission the pipeline's first stage in
2018 with the full line operational the following year. The project
stalled mid-2017 due to disputes regarding the gas contract, though
Gazprom says it remains on schedule.
Turkmengaz is leading the consortium of
national governments planning to build, own, and operate the 1,800-km
Turkmenistan-Afghanistan-Pakistan-India (TAPI) natural gas pipeline,
designed to carry 33 bcmy by 2022.
The Asian Development Bank (ADB) in 2005
estimated TAPI's cost at $7.6 billion, making the pipeline profitable
only at throughputs of 30-33 billion cu m (bcm)/year. The estimated cost
was nearly triple ADB's 2002 estimate of $2.6 billion. Persistent
delays have since raised TAPI's projected cost to $10 billion.
TAPI would run 200 km through Turkmenistan
(starting from Galkynysh gas field in Turkmenistan's eastern Mary
province), 773 km through Herat and Kandahar provinces, Afghanistan, and
827 km through Multan and Quetta, Pakistan, to end at Fazilka in
northern Punjab province, India
The pipeline would carry 90 million standard
cu m/day (MMscmd) of natural gas from the 16-tcf Galkynysh field
(formerly South Yolotan-Osman) under 30-year commitments, with India,
Pakistan, and Afghanistan (originally set to have received 38, 38, and
14 MMscmd, respectively). Afghanistan, however, has reduced its
requirement to just 1.5-4 MMscmd, opening the possibility of India and
Pakistan's share growing to as much as 44.25 MMscmd each.
India said its interest remained strong as of August 2017, with Afghanistan saying construction could begin as early as 2018.
GSPL India Gasnet Ltd. is building a 2,052-km
natural gas pipeline between Mehsana and Bhatinda. The project received
its environmental permits from the Indian government in May 2013. GSPL
expects the 42-in. OD pipeline to enter service in 2018 with a capacity
of 30-million cu m/day (mcmd). The pipeline will carry production and
imports from India's east coast to consumers in central and northern
parts of the country.
GAIL (India) Ltd. plans by 2018 to build a
1,825-km gas pipeline from Surat to Indian Oil Corp.'s (IOC) 15 million
tonne/year refinery in Paradip. The 36-in. OD west-to-east line passing
through Maharashtra and Chhattisgarh includes five spur lines totaling
124 km. Pipelay was underway as of November 2017.
Construction began in July 2015 on the first
phase of GAIL's Jagdishpur-Haldia natural gas pipeline. The 2,050-km
pipeline-922 km of 36-in. OD trunkline and 1,128 km of 12-30 in spur and
feeder lines-will connect eastern India to the national grid. The
initial phase will ship 7.4 million cu m/day (cmd), with total capacity
reaching 16 million cmd.
The pipeline will cross Bihar, Jharkhand,
West Bengal, and Uttar Pradesh states. It will pass through 13 districts
in Bihar, supplying refineries both there and in Barauni. It will also
supply local gas networks in Barauni, Gaya, and Patna. It is expected to
enter service in 2018.
IOC plans to build a nearly 2,000-km LPG
pipeline to ship cooking gas from Kandla port and a refinery at Koyali
east to consumers in Gorakhpur by 2020. The line would use 10.75 and
12.75-in. OD pipe to move 3.75 million tonnes/year.
The long-discussed Iran-Pakistan natural gas
pipeline has been given a new lease on life by the need to link a
planned LNG terminal at Gwadar, Pakistan, with consuming markets. A
700-km, 42-in. OD pipeline would run from Gwadar LNG east to Nawabshah
and access to the Sui Southern Gas Co. (SSGC) network. An 81-km leg from
Gwadar to the Iranian border could complete the pipeline once the
larger line has entered service. Pakistan has been slow to build its
section of the line due to lack of funding. The Iranian section of the
line is built.
Russia, meanwhile, has agreed to build a
pipeline in Pakistan connecting an LNG terminal in Karachi with Lahore.
The 42-in. OD, 683-mile pipeline would carry 1.2 bcfd north from the
coast starting in 2018. The Pakistani government in July 2017 asked SSGC
to build the section between Nawabshah and Karachi.
Europe
Gazprom and Germany's BASF SE in
August 2015 signed a memorandum of intent stipulating cooperation on
building the Nord Stream II gas pipeline. The companies would build
strings No. 3 and No. 4, connecting the Russian and German coasts under
the Baltic Sea and doubling the line's 55-bcmy capacity by 2019. E.On,
Shell, and OMV AG each previously had agreed to participate in building
the two strings. Intertek was awarded a project inspection and
expediting contract in December 2016. In April 2017, Allseas was
contracted for pipelay.
Russia in late 2014 decided against building
the 930-km South Stream natural gas pipeline across the Black Sea from
Russia to Bulgaria, citing delays on the part of the European Union in
taking the steps necessary to move forward. Gazprom Chief Executive
Alexei Miller and Mehmet Konuk, chairman of Botas Petroleum Pipeline
Corp., signed a memorandum of understanding on instead building an
offshore gas pipeline from the Russkaya compressor station (also South
Stream's starting point), under construction in the Krasnodar Territory,
across the Black Sea to Turkey (OGJ Online, Dec. 2, 2014).
The new pipeline, TurkStream, would have the
same 63 bcm/year overall capacity as South Stream, with 14 bcm/year to
be used in Turkey and the balance shipped to a border crossing with
Greece. The 448-Mw Russkaya station will provide as much as 28.45 MPa of
pressure, enough to have shipped gas on South Stream to Bulgaria
without intermediate compression.
Gazprom in 2016 received permits both for
construction and to conduct survey work in Turkey's territorial waters
on TurkStream's first two strings. The line's offshore section will
consist of four 15.75-billion cu m/year strings. Gazprom hired Allseas
Pioneering Spirit to conduct the 900-km offshore pipelay, which had
reached Turkish waters as of November 2017.
Partners in the Shah Deniz consortium made a
final investment decision (FID) in December 2013 on Stage 2 development
of the Caspian Sea natural gas field offshore Azerbaijan, triggering
plans to expand the South Caucasus Pipeline (SCP) through Azerbaijan and
Georgia, build the Trans Anatolian Gas Pipeline (TANAP) across Turkey,
and begin work on the previously selected Trans Adriatic Pipeline (TAP)
for shipment into Europe.
SCP expansion will twin the existing
Baku-Tbilisi-Ceyhan (BTC) pipelines through Azerbaijan and Georgia, as
well as adding two compressor stations to boost capacity by 16 bcmy.
Project plans call for 441 km of new 56-in. OD pipe; 385 km through
Azerbaijan and another 56 into Georgia, at which point the expansion
will connect to the existing SCP. The first additional compressor
station will be 3 km inside Georgia, collocated with an existing BTC
station near Rustavi. The second new station will be at a greenfield
site on the existing line 139 km downstream, west of Tsalka Lake,
Georgia. SCP's current capacity is 7 bcmy. BP expects work to be
completed by end-2018.
TANAP will run 1,800 km at an estimated cost
of at least $7 billion. The 48- and 56-in. OD pipeline will move as much
as 30 bcm/year by 2018, coinciding with first gas from Shah Deniz II.
TAP will transport as much as 20-billion cu
m/year of natural gas from Shah Deniz II through Greece and Albania to
Italy, from where it can be shipped further into Western Europe. The
project will use 36- and 48-in. OD pipe. Service, slowed by Italian
protestors, is now expected to begin in 2020. The 36-in. pipe will make
up the line's 115-km offshore section, with the 48-in. pipe used
onshore. Total planned length is 800 km.
Shah Deniz II will add 16 bcmy of gas
production to the roughly 9 bcmy of Shah Deniz Stage 1. Field
development, some 70 km offshore Baku in the Azerbaijan sector of the
Caspian Sea, includes two new bridge-linked production platforms; 26
subsea wells to be drilled with 2 semisubmersible rigs; 500 km of subsea
pipelines built at up to 550 m of water; the 16 bcmy upgrade to SCP;
and expansion of the Sangachal Terminal.
The Poland-Lithuania Gas Interconnector
(GIPL), designed to connect the Polish and Lithuanian gas transmission
systems, will enter service in 2021. The 28-in. OD pipeline would
include 310-357 km of pipe between Holowczyce, Poland, and the
Lithuanian border, and another 177 km from the border to Jauniunai,
Lithuania.
Middle East
Iraq began technical work in 2014 on
twin 1,043-mile pipelines-one crude oil, one associated fuelgas-running
from Basra to the Red Sea at Aqaba, Jordan. The oil pipeline, using
56-in. OD pipe to move 1-million b/d, will cross 422 miles inside Iraq
with the balance in Jordan. Jordan will keep 150,000 b/d for domestic
refining. Iraq is pursuing the project to decrease its dependence on the
Persian Gulf as an oil export route.
Iraq decided in August 2017 to cancel a
parallel gas pipeline, citing high costs and associated delays. The
pipeline was to have fueled the crude line's pumps, with alternative
power sources now being sought.
Saipem in February 2016 signed a memorandum
of understanding (MOU) with National Iranian Gas Co. (NIGC) for possible
cooperation on NIGC's proposed Iran Gas Trunkline IX (IGAT 9) and Iran
Gas Trunkline XI (IGAT 11) pipeline projects, which combined, would
cover a distance of 1,800 km (OGJ, Feb. 2, 2015, p. 72). Saipem did not
disclose details regarding timelines or estimated values for projects
under the MOUs. The MOUs followed suspension of long-standing
international sanctions on Iran that prohibited US and many European
firms from participating in development of the country's energy sector.
NIGC plans to build the 300-km
Iranshahr-Chabahar pipeline by 2018. The pipeline will use 240 km of
56-in. OD line and 60 km of 36-in. OD line, delivering natural gas to
power the Chabahar free trade and industrial zone. Iran began
construction in March 2017.
The National Iranian Gas Export Co. (NIGEC)
in 2016 hired Iranian Offshore Engineering and Construction Co. (IOEC)
and Pars Consultant Engineering Co. to perform survey and basic
engineering work on a 380-km pipeline intended to carry Iranian gas to
Oman. IOEC will complete the offshore study and Pars the onshore.
The onshore section of the pipeline would use
200 km of 56-in. OD pipe in Iran, with the offshore section running 180
km of 36-in. OD pipe from Kuhe Mubarak, Iran, to Sohar Port, Oman. The
onshore pipe would deliver gas from the IGAT VII pipeline to Kuhe
Mubarak. The two countries reached agreement on the project in February
2017. Delivery of 28 million cu m/day to Oman would begin in 2019.
Oman Gas Co. (OGC) plans to build a 221-km,
36-in. OD pipeline to deliver natural gas from Saih Nihayda in central
Oman to an industrial and maritime hub being developed in Duqm. OGC
signed Petrojet as contractor in late 2016 and expects the 25-mcmd
pipeline to enter service in 2019.
Africa
Uganda and Tanzania plan to build
the 897-mile, 24-in. OD heated East Africa Crude Oil Pipeline (EACOP),
bypassing Kenya as it transits between fields in Uganda and the
Tanzanian port of Tanga. The pipeline, engineered by Gulf Interstate
Engineering Co., would transport roughly 300,000 b/d to the Indian Ocean
for export.
Total SA suggested this route as an
alternative to mitigate security concerns regarding a previously
considered Kenyan passage. China National Offshore Oil Corp. Ltd. and
Tullow Oil are developing the project with Total. The line is expected
to enter service in 2021.
Ethiopia and Djibouti plan to build a 700-km,
40-in. OD natural gas pipeline to transport Ogaden basin gas to a
floating LNG liquefaction plant offshore Djibouti. China's Poly-GCL is
developing the project with a scheduled 2020 startup date. The 3-million
tonnes/year (mtpy) plant, fed by the 2-billion cu m/year pipeline,
would be sited at Damerjog port near the Djibouti-Somalia border and
expandable to 10 mtpy.
Bulk Oil Storage and Transportation Co. Ltd.
(BOST) in late 2015 awarded a front-end engineering and design contract
to Penspen for development of Ghana's Natural Gas Interconnected
Transmission System (NGITS). The planned 750-km Phase 1 buildout would
run from Aboadze to Tema, and from Prestea to Buipe, via Kumasi. The
project will use 24-in. OD pipe with completion expected in 2018. A
construction contract was signed in April 2017.
No comments:
Post a Comment